The research progress on lifting technique of 120 m span steel roof truss
Abstract
Assembling and mounting of steel truss of super large span roof are analyzed. Steel truss factory prefabricated parts are used. An overall jig frame is sectionally assembled on site and lifted after being assembled in sections. Then, it is assembled in place in a mode
that a temporary support jig frame is erected on site, so that large lifting and transportation equipment can be reduced. Thus, the cost is saved and the construction period is shortened.
Keywords
steel truss; assembling; sectional lifting; jig frame
Full Text:
References
View
DOI: https://doi.org/10.26789/AMS.2017.01.004
Refbacks
- There are currently no refbacks.
Copyright (c) 2017 Han-Shi Lu, Min-Ming Lu