In order to solve the problems of crane operating range in blind areas and insufficient weight support of crane for steel structure bubble roof lifting construction, it is a must to design propelling crane on the roof, so that it can move on selected routes, completing the lifting work of steel roofing bubble. Mainly introduce the technical measures and related technical preparation of propelling crane on the roof for steel structure lifting process, to ensure the originality of steel structure during lifting process and safety of construction work,also to guarantee the progress of steel structure lifting work.
Keywords
Steel propelling; Hoisting; Crane